Photos: All Marsa Junction Project flyovers now open

default

Tista' taqra bil- Malti.

All of the seven flyovers of the Marsa Junction Project are now open to road users, Infrastructure Malta announced on Saturday morning, saying that the project will facilitate direct, uninterrupted connections between the major routes converging at the busiest intersection of the Maltese road network.

Infrastructure Malta reopened the three flyovers completed in 2019 in the northbound direction, after they had been used in contraflow as a temporary southbound diversion route during the last 14 months, on Saturday morning.

The final works were completed this week. The works included the topmost asphalt layer and expansion joints, which could not be carried out whilst they were still required in the southbound direction.

These three flyovers are now forming direct, two-lane connections from the northbound carriageway of Santa Lucija Avenue and the northbound carriageway of Giuseppe Garibaldi Road (Luqa) towards Aldo Moro Road, Marsa, in the direction of Santa Venera, Qormi, Hamrun, Valletta and other localities in central Malta.

Only last month three flyovers beneath them, at this new grade-separated junction’s intermediate level were opened.

These flyover structures are serving the opposite direction to connect Aldo Moro Road’s southbound carriageway with Santa Lucija Avenue and Garibaldi Road, towards Santa Lucija, Tarxien, Luqa, Gudja and other destinations in the south of Malta.

The seventh flyover structure of this project, which links the northbound carriageway of Santa Lucija Avenue with new lanes to the Addolorata Cemetery and a new park and ride that is still under construction and with Il-Gvern Lokali Road, towards Qormi (Turkish Cemetery area), was also recently opened.

Infrastructure Malta explained that workers are now focusing on the last stretch of this project’s new lanes, which will connect the southbound carriageway of Aldo Moro Road with Sir Paul Boffa Avenue, towards Corradino, Paola and Cottonera. This final link of the new multi-level junction will be ready by the end of the year.

The new footpaths and pedestrian bridges, bus lanes, bus lay-bys, park and ride areas and segregated cycling tracks are in their final stages as well. The new walking and cycling track connecting Paola, Tarxien and Santa Lucija with the Marsa Sports Grounds area of Marsa will be open within a few weeks.

The €70 million Marsa Junction Project is co-financed through the European Union’s Cohesion Fund and the Connecting Europe Facility.